EGAT invites bids for hydro-floating solar hybrid project at the Ubol Ratana dam

The deadline for bidding is 9 March and bidding documents are available until 15 February.

Electricity Generating Authority of Thailand (EGAT), Thailand’s vertically integrated state utility, invites sealed bids from individual bidders or joint ventures by March 9 for the design, manufacture, fabrication, shop tests, supply, delivery to site, insurance, construction, installation, testing, commissioning and on-site training for a hydro-floating solar hybrid project at the Ubol Ratana dam.

The project must comprise a crystalline silicon PV solar powerplant not less than 31.19 MWp and not more than 31.2 MWp. The hybrid pilot project will generate electricity from both hydropower and solar power and comprise an energy management system (EMS) along with battery energy storage system (BESS) to enhance efficiency and continuity of power generation. The scope of supply also includes a floating PV system, anchoring and mooring system, 22 kV electrical system and transmission lines, control and monitoring system and related software system.

The Ubol Ratana Dam is a multi-purpose dam in Khon Kaen Province, in the northeastern area of Isan, which provides electricity generation, irrigation, flood control, transportation, fisheries, and serves also a as tourist attraction. Its 32 m-high earth core rockfill dam, constructed in 1964, impounds the Nam Phong, which flows into the Chi River and thence to the Mun River, a tributary of the Mekong River, creating a reservoir with a maximum storage capacity of 2.263 x 106 m3.

It has an associated 25.2 MW hydropower plant, comprising three Kaplan turbines, each with an installed capacity of 8.4 MW, which generates an average of 57 GWh a year.

The bidding documents for Bid No. EGAT 9/2563-UR-FPV (UBOLRATANA DAM HYDRO-FLOATING SOLAR HYBRID PILOT PROJECT) are available upon written request and proof of payment of a non-refundable fee of US$ 660/THB 20 000 to ned_pro@egat.co.th. Bidding documents are available for purchase until 15 February by bank transfer or telegraphic transfer to EGAT’s account no. 109-6-01958-2 (swift code: KRTHTHBK), Krung Thai Bank Public Company Limited, Bangkruai Branch, Nonthaburi. For more details and to download the Request Form for purchasing the bidding documents, visit www4.egat.co.th/fprocurement/biddingeng.

For more information, contact: International Procurement Department – Generation, Power Plant Development and Renewable Energy Segment Procurement and Inventory Management Division, Room No.303, 3rd Floor, Building No. TOR 082 Electricity Generating Authority of Thailand, Bang Kruai, Nonthaburi 11130, Thailand; Tel: +662 433 9774; Fax: +662 433 6317; Email: nathatai.jat@egat.co.th; ned_pro@egat.co.th.